Project Facts

Mick George Ltd was associated with the Earthworks and Soil Stabilisation for a Compound Site to enable Rail upgrades.

The scheme covers one of the last major line routes remaining to be electrified', following the pause in the national electrification programme' back in 2015. Known as 'London to Corby Electrification', the focus is mostly on Beford to Corby. In addition to wiring the route, additional tracks are being installed to increase capacity.

Service: Site Clearance, Earthworks, Aggregates, Stabilisation
Project: Train Station Compound
Location: Sharnbrook
Client: Carillion PLC
Value: £135,000
train station compound

Works

- Site Clearance

- Strip Topsoil and Construct Temporary Bunds

- Install Sub-base

- Install Surface to Car-park, Footpaths and Access Roads

- Stabilise Formation to 15% CBR

- Regrade Areas

- Import Place and Compact Primary Type 1 Aggregate

- Supply and Install 1.8m Chainlink Fence with Track Access Gates