Record Breaking A14 Concrete

Last week, Mick George Concrete completed a 'record breaking' pour for for Section 2 – Buckden Road Bridge on the A14 Highway Improvement Scheme.

Please see enclosed a link to video footage: https://www.youtube.com/watch?v=tcsR66ElK58

The footage represents the largest single pour made on this section of the project to date.

710m3 of Concrete was supplied by Mick George to form the first half of the bridge deck, with the second half of the pour scheduled for next week.

In its entirety, 1,500m3 of Concrete will be supplied, equating to 2,800 tonnes of aggregates, and 16 trucks completing 180 dedicated, restricted distance movements from the onsite and nearby batching plants, in just 12-hours.