Project Facts

Service:Asbestos Survey & Removal
Client:Coulson Group Ltd
Location:Peterborough
Project:Town Hall
Value:£18,198
peterborough town hall

The Brief

Mick George Ltd was associated with the fully enclosed removal of AIB to the side of radiators, shuttering and floor boards underneath radiator pipework, within the 1st-floor south wing of Peterborough Town Hall.  The project included Asbestos Surveys and the removal of licensed and non-licensed asbestos materials.

Schedule

• ASB5 14-Day notification to the HSE
• Preparation of HSE approved plan of work
• Set up of full enclosures in accordance with MGE Standard Operating Procedures
• Removal of AIB to radiators and above pipework - 1st floor South Block
• Removal of vinyl floor tiles to stairs; removal of toilet cisterns from x 2 shop units

• Disposal of all ACMs and provision of hazardous waste consignment notes
• 4 stage air clearances and personal monitoring
• Duration of works: 12 days
• Size of Job (area or volume): x 3 Enclosures amounting to Approx x 1 40 yard enclosed skip

Location

Testimonials

Whenever Asbestos is discovered on one of our projects, it is never something that is particularly well greeted as it’s usually a difficult and time consuming job to remove. That said, the ‘Environmental’ division at Mick George Ltd has done a tremendous job taking care of all aspects, from surveying through to disposal.